(also see more pictures
here) for newer updates
click here
received and posted July 18, 2008
ALL:
Just a brief note for everyone on a few items.
De-Watering:
Friday July 11, 2008 We started De-Watering the
marina basin. As of July 18 the basin has been pumped down to just a few
feet of water remaining in the main channel ways. Attached are a few
pictures.
The electric shock boat used to collect and move fish
There will be more
posted on the department web site in the coming weeks.
The Ohio Division of Wildlife was on site July 17,
with the electric shock boat assisting in collecting and moving native
fish from the marina basin into Lake Erie.
We continue to work with Ohio EPA and the US Army
Corp of Engineers to assure compliance with our permits. This next week,
we will finish the dewatering and we are planning to start removing
parts of the center peninsula.
The north parcel is our first site area to have
marina materials placed in.
As we begin the deepening and shaping of the marina
basin large equipment will be moving across Fox Rd. and throughout the
construction zone. Please help us have a safe project. Drive / Bike
carefully.
Lake Erie Water Snakes:
We have relocated 250 snakes so far during this
project. We appreciate the effort of Kristin and Keith who sincerely put
forth the effort to keep us on track with this aspect of the project -
protecting an endangered species.
Dock Construction:
The project construction bids submitted by various
contractors were "opened" July 10, 2008. There were several bidders and
it is encouraging to see the interest in the project. We hope to have
the "low bidder" chosen this next week.
Next Open House: Scheduled for July 28, 2008 3:00PM
- 4:30PM Just on the south side of Aunt Irma's in the shade.
Thank you,
Scott Doty
Regional Manager
Lake Erie Islands state Park
received and posted July 12, 2008
ALL:
Just a brief note for everyone on a few things.
De-Watering:
Friday July 11, 2008 We have started to
De-Water
the marina basin. We continue to work with Ohio EPA and the US army Corp
of Engineers to assure compliance with our permits. This is great news
as we can now proceed in preparing for the "heavy" work in the marina
basin. Once this is de-watered we will begin the cleaning and deepening
of the marina basin to a depth of 10 feet. We will also start shaping
the basin to the new design plan as we have been depicting over the last
couple of years.
As we begin the deepening and shaping of the marina
basin large equipment will be moving across the Fox Rd. and throughout
the construction zone. Please help us have a safe project. Drive / Bike
carefully.
The Ohio Division of Wildlife will be assisting in
collecting and moving fish from the marina basin into Lake Erie, as we
get it pumped down.
Web Page:
We have appreciated Mike Gora's interest and
assistance in posting information on the Middlebass.org web page. I have
received comments back expressing appreciation for this. I hope Mike
feels the information worthy to continue to post. Thank You Mike.
I have mentioned we would have an ODNR web site in
the future. Well it has happened. Here is a direct link to ODNR's Middle
Bass Island State Park web page. You can see the design "sketch" here if
you click on the tab "Photos".
http://www.dnr.state.oh.us/parks/middlebass/tabid/766/Default.aspx
Webmaster's note: The pool shown in the design sketch
is not a swimming pool. It is a
vernal
pool.
Lake Erie Water Snakes:
We have relocated 240 snakes so far during this
project. We appreciate the effort of Kristen and Keith who sincerely put
forth the effort to keep us on track with this aspect of the project -
protecting an endangered species.
Dock Construction:
The project construction bids submitted by various
contractors were "opened" July 10, 2008. There were several bidders and
it is encouraging to see the interest in the project. We hope to have
the "low bidder" chosen this next week.
Elevated Storage Tank:
The elevated water storage tank for the state
park's water system is being advertised. We plan on having a contractor
chosen for this part of the project this fall.
Next Open House: Tentatively Scheduled for July 28,
2008 Afternoon time to be announced.
As an added bonus :) for those that may be interested this is a link for the
home page for all of the Ohio State Parks.
Scott Doty
Regional Manager
Lake Erie Islands state Park
received and posted June 23, 2008
All:
A few items to share since our last note
Dock Construction: The new dock construction
"Pre-Bid" meeting was conducted 6/20/08. We had approximately 50 people
in attendance. We extend a Thank You to the Ottawa County Visitors
Bureau in allowing us to use the conference room at their facility.
Interested Contractors are to have their
bids submitted by July 10, 2008. We anticipate it will take
approximately 60 days to give the contractor awarded the job, their
notice to proceed. New docks will begin to be built.
This means that next summer we will see new
docks in the marina.
Marina Construction: Continues
De-watering of the marina basin is the next
big step we are preparing for. This will start the beginning of
July. The East wall of the marina had been breached this past
winter. It has been "shored up" to allow pumping to start. The
pumps are being, (have been), placed.
Here is a picture taken fall of 2007.
Fall water levels are normally lower than spring and summer,
water levels. This picture shows the lower fall water level.
During "normal" water levels - waves are washing over the steel
and through the gaps in the steel plating. You can see here how
the marina walls, made with this material, are collapsing. This
material and construction is found in several areas including
the marina entrance channel.
The de-watering program is starting
later than we had hoped. The reason for this delay was weather
and permit related. The cold spring, and the later than
anticipated ice thaw, not only resulted in the ferry boats
delaying their start-up, it also slowed our contractor getting
equipment to the island as well. Permits also have influenced
our timing of de-watering, as they determine the "window of
time" we can do "in-water" work. There is a restricted window
starting April 15 through June 30 related to the spawning season
of fish. Once we are past this restricted window we can begin
to de-water the basin. The contractor anticipates de-watering
the entire basin will take a week to 10 days.
Special note: The Construction
Zone is considered anything within the Snake Fence .
Please remain outside of the fenced area as required by safety
regulations of construction sites.
We currently anticipate having people
from our Division of Wildlife on-site July 7, to help remove
fish as the basin is de-watered.
I Hope this helps to keep you all informed
Thank you,
Scott Doty
Regional Manager
Lake Erie Islands State Park
received and posted June 7, 2008
All:
A few items to share since our last note.
The Open house conducted June 6, on the island was
well attended. We had an estimated 25 - 30+ people stop by and talk with
some of our group between the hours of 3P and 6P. We were a little late
getting started, (arriving). We appreciated your patience with us.
Several questions that seemed to be asked more
frequently than some others were:
The marina will be deepened to 10 feet of depth
The project is still on track with the marina
to be usable next summer
The marina will have a design capacity of
around 340 slips, we will be planning on starting dockage of close to
240 (includes the yacht club)
Seasonal dockage will be a part of the marina
dockage plan.
We will plan another open house next month.
The clearing of areas for future fill sites is
done.
Other Items of noteworthiness:
Dock Construction Bid: The contract is to be
advertised June 17th. This is how we notify possible contractors who may be
interested in the job so they can submit a bid on the project.
Burning: We have completed all burning we had
planned to do this spring. There will be no more burning until after
September 2, 2008.
Our Lake Erie Water Snake Team has caught 130
snakes so far since construction started in May.
The contractor will be having stone delivered in
the future.
Some of this stone will be the large stone
referred to as "armor stone". Armor stone is usually stone of a size
that weighs 4 - 8 tons each and may be as large as 6' to 8' around. A
picture of one such stone is below if you wish to look at one.
The bulk of the large stone is for the
breakwalls and revetments. The project calls for a quantity of about
33,000 tons of ODOT "C" stone through 4-8 ton armor. ODOT "C" Stone is
about 12" x 12". LaFarge (Quarry in Marblehead) has about 5,000 tons of
armor produced for the project (about 20%). As for the smaller stone
sizes the majority of that product is produced and currently available.
Reminders:
The contractor has put steel plates on Fox Road
where they are crossing over the road. This will protect the roadway from
the heavy equipment crossing it. There are 3 crossing areas; 1 by Aunt
Irma's, Just North of Jim Roesch's former marina and next to St. Hazards.
Signs will also be coming warning of truck
crossings. A few other safety barrels will be erected for safety. We
ask everyone to remember to drive carefully through the
construction zones & remind others as well.
Lake Erie Water Snakes - LEWS Kristin has a full
time LEWS specialist, Keith Hanson. Keith will be on the island working
alongside the contractor checking snake traps and where the heavy equipment
is working within the snake fenced area.
Keith and Kristin will be relocating any snakes
found within the area to areas outside the fenced construction zone. We
welcome Keith to the project. If you see snakes with some colorful
paint markings (blue or green). These are ones they have relocated.
Raccoons seem to be very inquisitive creatures
wanting to see if things are truly greener on the other side of the
fence. We have found where they are climbing or tearing the fence to
get on the other side.
The snake fence is also a construction safety zone
fence. We ask everyone to stay outside of the construction zone.
A new person for on-site contact regarding
construction concerns is Rob Stanley. Rob is working for BBCM, our
Consultant with this part of the project. Rob is available for you to
contact on the island with questions or by cell phone 614-578-8266. You are
also welcome to contact me as in the past with questions.
Marina de-watering will begin by the end of the
month. As this happens we will ask that you remain outside the construction
fence for safety reasons. We will be posting pictures in the future of the
progress as it happens.
Mike Gora has allowed our notes here to be posted
on his web site, Middlebass.org. You can find notes there as well. We have
a date the Ohio State Park web site will be up and running, June 15 or
shortly there about. We hope to use this site for all to see specific
updates about the marina.
I Hope this helps to keep you all informed
Thank you,
Scott Doty
Regional Manager
Lake Erie Islands state Park
received and posted June 1, 2008
All:
Mark your calendars for June 6, 2008 3PM - ?? (No
later than 6 PM)
The first of a number of summer "Open House"
opportunities is scheduled for Middle Bass Island State Park, Marina.
We are hoping the weather cooperates and this will be
done on the island behind Aunt Irma's.
The format of an "open house" is you will have the
opportunity to meet with ODNR representatives and ask questions about the
project. We will have several display boards available to help show the overall
construction plan. This will not be a formal meeting presentation, so if you
are not able to be there at 3PM, but can be there at 4:30 or so that is fine.
We will be there to answer questions.
Thank you,
Scott Doty
Regional Manager
Lake Erie Islands State Park
received and posted May 22, 2008
A few items to share since our last note
Dock Construction Bid: This document is all
but done. There are a few corrections to be made to the final draft and
then signatures. We should see the document released in the next few
weeks - providing there are no hitches.
Water and Sewer Lines: The planning is nearing
completion.
This project includes the construction of
an elevated water tower. The design and capacity specs. will be for
the current use demands for LEU and the park. We are also
incorporating design features that will allow for future expansion
or decreases in tank size, based on future water demands and
regulations dictate.
Electric Utility: Service and supply design is
underway
Buildings and other infrastructure: We are
putting information together for architectural planning to start.
Burning: We have been permitted to burn. The
contractor has been working on this aspect of the project. Burning is
permitted through May 25 and then after September 2, 2008.
Lake Erie Water Snakes - LEWS Kristin has a
full time LEWS specialist, Keith Hanson. Keith will be on the island
working alongside the contractor checking snake traps and where the
heavy equipment is working within the snake fenced area.
Keith and Kristin will be relocating any
snakes found within the area to areas outside the fenced
construction zone. We welcome Keith to the project. If you see
snakes with some colorful paint markings (blue or green), these are
ones they have relocated.
They have caught 30 snakes so far since
construction started a few weeks ago.
The contractor has put steel plates on Fox road
where they are crossing over the road. This will protect the roadway
from the heavy equipment crossing it. There are 3 crossing areas; 1 by
Aunt Irma's, Just North of Jim Roesch's former marina and next to St.
Hazards.
There is a bump to these currently. Some
cold patch will be used to soften the approach.
Signs will also be coming warning of truck
crossings. A few other safety barrels will be erected for safety.
We ask everyone to remember to drive carefully through the
construction zones & remind others as well.
The snake fence is also a construction safety
zone fence. We ask everyone to stay outside of the construction zone.
A new person for on-site contact regarding
construction concerns is Rob Stanley. Rob is working for BBCM, our
Consultant with this part of the project. Rob is available for you to
contact on the island with questions or by cell phone 614-578-8266. You
are also welcome to contact me as in the past with questions.
Marina de-watering will begin by the end of the
month. As this happens we will ask that you remain outside the
construction fence for safety reasons. We will be posting pictures in
the future of the progress as it happens.
We are planning on hosting several "open
houses" this summer on the island for opportunity to answer questions
and show the revised master plan and construction plans.
Mike Gora has allowed our notes here to be
posted on his web site, Middlebass.org. You can find notes there as
well. We have a date the Ohio State Park web site will be up and
running, June 15 or shortly there about. We hope to use this site for
all to see specific updates about the marina.
Thank you,
Scott Doty
Regional Manager
Lake Erie Islands State Park
received and posted May 9, 2008
I, along with several others, officially met with the
contractor's crew on Middle Bass Island Monday May 5, 2008.
As promised last week I would be giving a more detailed
update this week regarding the project. There are still things being worked up
so I doubt this note will answer all the questions, but it will give you a heads
up.
The contractor has started erecting the snake fence
for construction.
Parking: I have asked for your help with this
item before and it seems we still need to get the word to several
people. Parking in the field along the south side of the old runway
next to Fox Rd. is not permitted. We are trying to establish the
snake protection fence for construction. The longer it takes for this
to happen - the longer some construction start-up is delayed. If you
know of anyone parked in this area, please contact them to move their
vehicle. Options are Roesch's parking area. Any assistance in this
matter is appreciated.
Once the snake fence is established The Snake Lady,
(Kristin), and her crew, will begin relocating the snakes from within the
construction zone to outside the zone. Kristin has shared they will be
marking the snakes with either a Green or Blue paint. This will help them
determine habits of the snakes they have relocated and if there are any
getting back in.
Once Kristin has had time to relocate the snakes
from the construction zone she will allow construction to start in the
marina area. Again - emphasizing the importance of getting the cars
moved & the fence completed.
De-Watering of the marina basin. This will begin in
2 or 3 weeks.
Tree rubble burning - The contractor has coordinated
with the EPA, permits have been done, if there is any burning to be done
this spring it will be done before May 21.
The contractor has a crew of just a couple people
this week to start the fence. Over the next several weeks this will
increase to a dozen or so people.
The closed off marina channel will be used for
the equipment barge to anchor in. It will be arriving soon. The barge
will be going & coming as it will be used to haul supplies & materials
from the mainland. Docking in this area is prohibited.
As has been arranged with the county engineer's
office construction can be underway seven days a week. Heavy equipment
on the roads will be restricted to Monday through Friday mornings. This
we hope will alleviate concerns regarding the weekend traffic problems.
The Lake Erie Water Snake is still listed as an
endangered species. There has been evidence of intentional harming of one
of these protected snake. I would like to remind all of the protected
status of the snake and we also share this with island guests so they are
aware of this as well.
If you have questions or comments feel free to drop a
note back.
Thank you,
Scott Doty
Regional Manager
Lake Erie Islands state Park